Welcome to Sugar Land Regional Airport:
Project & Construction Updates
Sugar Land Regional Airport is dedicated to enhancing business operations through world-class services, airfield improvements, and a continuous commitment to clientele. This initiative has led Sugar Land Regional Airport to be the fourth largest airport in the greater Houston area, and the foremost general reliever airport in the southwest sector. As Sugar Land Regional Airport makes enhancements, project and construction updates will be provided on runwayupdate.com.
Scheduled Closures
May 15, 2024; May 16, 2024; May 17, 2024
10:00pm - 6:00am DST (0300z-1100z)
Due to progress being made with the taxiway relocation project, we will be closing Runway 17-35 at night. Keep in mind these dates are tentative and subject to change due to weather or other circumstances. Closure dates are scheduled on a week-by-week basis.
Notice to Airmen:
Check NOTAMs here >
Enter “SGR” to view
!SGR 05/028 SGR RWY 17/35 CLSD EXC 24HR PPR 281-275-2125 DLY 0300-1100 2405150300-2405181100
!SGR 02/032 SGR SVC ATIS 118.125 U/S 2402292306-2407312359
!SGR 04/029 SGR RWY 17/35 CHANGED TO 8000FT X 100FT. DECLARED DIST: RWY 17 TORA 7960FT TODA 7960FT ASDA 6960FT LDA 6580FT. RWY 35 TORA 7960FT TODA 7960FT ASDA 7010FT LDA 5066FT. 2404260300-PERM
!SGR 03/038 SGR TWY M CLSD 2403291100-PERM
!SGR 03/039 SGR TWY K CLSD 2403291100-PERM
!SGR 03/040 SGR TWY L CLSD 2403291100-PERM
!SGR 03/041 SGR TWY A NORTH OF TERMINAL RAMP COMMISSIONED CONC LGTD 2403291100-2405161300
!SGR 03/042 SGR TWY A1 COMMISSIONED BTN APCH END RWY 17 AND TWY A CONC LGTD 2403291100-2405161300
!SGR 03/043 SGR RWY 17/35 WIP CONST ADJ E EDGE BTN A1 AND A3 2403291100-2407312359
Current Projects
Taxiway Relocation
Runway 17/35 Rehabilitation Project
Upcoming Projects

There are no upcoming projects at this time.

Completed Projects